Map
Reference
(see below) |
Location of Construction |
Construction Activity |
Road Closure |
Duration |
Information |
1 |
9th St Bridge Over Sydenham River |
Final construction of curbs, sidewalks, asphalt and landscape details will be completed in the spring of 2011 |
Currently, the NEW 9th St Bridge is open to all traffic. Temporary closures are expected spring of 2
|
Construction is expected to restart in the spring of 2011and should be completed by July 2011 |
During construction in 2011 the bridge will be temporarily closed to traffic and a detour will be provided. Additional formation will be provided later in 2011 |
2 |
9th St E from 1st Ave E to 2nd Ave E.
And, 9th St W from 2nd Ave W to 1st Ave W. |
Bell telephone communication cables installation |
Temporary lane closures daily during construction
NO |
Construction COMPLETED May 2011 |
This Project will be started in the spring of 2011 |
3 |
10th Street East from Lamson Crescent to 16th Avenue East. |
New road construction.
Phase 2 includes guard rails, asphalt,curbs, traffic signals, pedestrian crossing and landscaping. |
Construction activities are limited to the unopened road allowance. No through traffic is allowed.
|
Phase 1 Construction to be completed spring 2011 |
Information on this project can be obtained by contacting Engineering at 519 376 4530.or Gamsby and Mannerow at 519 376 1805 |
4 |
10th St E from 9th Ave E to 11th Ave E |
Sidewalk installation and driveway remediation |
NO road closures are expected. temporary lane closures are
|
Construction to be completed spring 2011 |
Work continues from last fall to install new sidewalks on 10th St E This will connect to 10th St E that is expected to open in 2011. |